top of page
Search

Construction Updates - Feb 2020

pratapsaipurvi

Updated: Feb 22, 2021

- For A Block, Roofing is completed till the 10th floor. Pillaring work is completed for the

11th floor and roofing work is in progress. Brickwork is completed till the 5th floor and is

in progress on the 6th floor. Plastering work is finished till the 5th floor. 1st coat of wall

putty is completed till 2nd floor, Plumbing and electrical works are started.

- For B Block, Roofing is completed till 9th floor and Pillaring is in progress for 10th floor.

Brick work is completed till 3rd floor and is in progress in 4th floor.

- For C Block, Roofing is completed till 6th floor and Pillaring is in progress for 7th floor.

Brick work is completed till 3nd floor and is in progress in 4rd floor.

- For D Block, Roofing is completed in 2nd floor and pillaring is in progress in 3rd floor.










Comments


Commenting has been turned off.
bottom of page