Construction Updates - June 2020

Updated: Jun 21

- For A Block, Roofing is completed till the 13th floor. Pillaring is in progress for 14th

floor and roofing work is in progress. Brickwork is completed till the 9th floor and is in

progress on the 10th floor. Plastering work is finished till the 5th floor. 1st coat of wall

putty is completed till 5th floor, Plumbing and electrical works are started.

- For B Block, Roofing is completed till 13th floor and Pillaring is in progress for 14th

floor. Brick work is completed till 9th floor and is in progress in 10th floor.

- For C Block, Roofing is completed till 9th floor and Pillaring is in progress for 10th floor.

Brick work is completed till 6th floor and is in progress in 7th floor.

- For D Block, Roofing is completed till 5th floor and Pillaring is in progress for 6th floor.

Brick work is completed till 3th floor and is in progress in 4th floor.







519 views

KEEP IN TOUCH

Screenshot%202020-06-11%20at%206.42_edit

Building Highly Designed, Quality and Trustworthy Homes for 12 years. 

EXPLORE

  • Facebook
  • YouTube

@2020 by Sai Purvi Developers