- For A Block, Roofing is completed till the 13th floor. Pillaring is in progress for 14th
floor and roofing work is in progress. Brickwork is completed till the 9th floor and is in
progress on the 10th floor. Plastering work is finished till the 5th floor. 1st coat of wall
putty is completed till 5th floor, Plumbing and electrical works are started.
- For B Block, Roofing is completed till 13th floor and Pillaring is in progress for 14th
floor. Brick work is completed till 9th floor and is in progress in 10th floor.
- For C Block, Roofing is completed till 9th floor and Pillaring is in progress for 10th floor.
Brick work is completed till 6th floor and is in progress in 7th floor.
- For D Block, Roofing is completed till 5th floor and Pillaring is in progress for 6th floor.
Brick work is completed till 3th floor and is in progress in 4th floor.