Construction Updates - September 2020

- For A Block, Roofing is completed till the 16th floor. Pillaring is in progress for 17th floor and roofing work is in progress. Brickwork is completed till the 11th floor and is in progress on the 12th floor. Plastering work is finished till the 5th floor. 1st coat of wall putty is completed till 5th floor, Plumbing and electrical works are completed till the 10th floor and is in progress on the 11th floor.


- For B Block, Roofing is completed till 16th floor and Pillaring is in progress for 17th floor. Brickwork is completed till 11th floor and is in progress in 12th floor.


- For C Block, Roofing is completed till 13th floor and Pillaring is in progress for 14th floor. Brickwork is completed till 8th floor and is in progress in 9th floor.


- For D Block, Roofing is completed till 9th floor and Pillaring is in progress for 10th floor. Brickwork is completed till 5th floor and is in progress in 6th floor.







200 views1 comment