- For A Block, Roofing is completed till the 20th floor. Pillaring is in progress for 21st floor
and roofing work is in progress. Brickwork is completed till the 14th floor and is in progress on the 15th floor. Plastering work is finished till the 9th floor. 1st coat of wall putty
is completed till 8th floor, Plumbing and electrical works are completed till the 14th
floor, and is in progress on the 15th floor.
- For B Block, Roofing is completed till 21th floor and Pillaring is in progress for 22nd
floor. Brick work is completed till 14th floor and is in progress in 15th floor. Plastering
work is finished till the 9th floor.
- For C Block, Roofing is completed till 18th floor and Pillaring is in progress for 19th
floor. Brick work is completed till 13th floor and is in progress in 14th floor. Plastering
work is finished till the 5th floor.
- For D Block, Roofing is completed till 14th floor and Pillaring is in progress for 15th
floor. Brick work is completed till 9th floor and is in progress in 10th floor.Plastering
work is finished till the 5th floor.