- For A Block, Roofing is completed till the 17th floor. Pillaring is in progress for 18th
floor and roofing work is in progress. Brickwork is completed till the 12th floor and is in
progress on the 13th floor. Plastering work is finished till the 5th floor. 1st coat of wall
putty is completed till 5th floor, Plumbing and electrical works are completed till the
11th floor, and is in progress on the 12th floor.
- For B Block, Roofing is completed till 17th floor and Pillaring is in progress for 18th
floor. Brick work is completed till 12th floor and is in progress in 13th floor.
- For C Block, Roofing is completed till 14th floor and Pillaring is in progress for 15th
floor. Brick work is completed till 9th floor and is in progress in 10th floor. Plastering
work is finished till the 5th floor.
- For D Block, Roofing is completed till 11th floor and Pillaring is in progress for 12th
floor. Brick work is completed till 5th floor and is in progress in 6th floor.Plastering work
is finished till the 5th floor