top of page
Search

Construction Updates - October 2020

pratapsaipurvi

Updated: Feb 22, 2021

- For A Block, Roofing is completed till the 17th floor. Pillaring is in progress for 18th

floor and roofing work is in progress. Brickwork is completed till the 12th floor and is in

progress on the 13th floor. Plastering work is finished till the 5th floor. 1st coat of wall

putty is completed till 5th floor, Plumbing and electrical works are completed till the

11th floor, and is in progress on the 12th floor.

- For B Block, Roofing is completed till 17th floor and Pillaring is in progress for 18th

floor. Brick work is completed till 12th floor and is in progress in 13th floor.

- For C Block, Roofing is completed till 14th floor and Pillaring is in progress for 15th

floor. Brick work is completed till 9th floor and is in progress in 10th floor. Plastering

work is finished till the 5th floor.

- For D Block, Roofing is completed till 11th floor and Pillaring is in progress for 12th

floor. Brick work is completed till 5th floor and is in progress in 6th floor.Plastering work

is finished till the 5th floor




 
 
 

Comments


Commenting has been turned off.
bottom of page