- For A Block, Roofing is completed till the 21th floor. Pillaring is in progress for 22nd
floor and roofing work is in progress. Brickwork is completed till the 17th floor and is in
progress on the 18th floor. Plastering work is finished till the 13th floor. 1st coat of wall
putty is completed till 12th floor.
- For B Block, Roofing is completed till 22nd floor and Pillaring is in progress for 23rd
floor. Brick work is completed till 15th floor and is in progress in 16th floor. Plastering
work is finished till the 13th floor.
- For C Block, Roofing is completed till 19th floor and Pillaring is in progress for 20th
floor. Brick work is completed till 13th floor and is in progress in 14th floor. Plastering
work is finished till the 5th floor.
- For D Block, Roofing is completed till 16th floor and Pillaring is in progress for 17th
floor. Brick work is completed till 11th floor and is in progress in 12th floor.Plastering
work is finished till the 5th floor