- For A Block, Roofing is completed till the 13th floor. Pillaring is in progress for 14th floor and roofing work is in progress....
pratapsaipurvi
Jun 11, 20201 min read
621 views

Construction Updates - March 2020
- For A Block, Roofing is completed till the 12th floor. Pillaring work is completed for the 13th floor and roofing work is in progress....
pratapsaipurvi
Mar 1, 20201 min read
84 views

Construction Updates - Feb 2020
- For A Block, Roofing is completed till the 10th floor. Pillaring work is completed for the 11th floor and roofing work is in progress....